The Pyramid Project

 Home Up Shamanic Tour Missions Design Art Forum 

 

Phase 4

 

Phase 4 Objective: “Build Permanent Platform & Float"
By 08 August 2008 (2¼ months)

 

Phase 4 Objectives Discussed"

·        To float a pyramid on bottles is seen by many as an engineering achievement and this will have been promoted to aid bottle collection. The achievement is also environmentally sound in the sense that rubbish is being recycled for a good use

·        At the beginning of Phase 4 we have a structure that is 126 tons floating on 100 4m²rafts that have a capacity to lift 193 tons, that is 65% utilisation of the lift

·        By the end of Phase 4, by filling Rings 1 & 5 with bottles and preparing rings 2, 3 & 4 with Topa ready to take more bottles as they are collected, the structure will weigh 272 tons. The lift with rings 1 & 5 (309 tons) coupled with around 16 remaining rafts (31 tons lift) will be 340 tons, that is apparently a lift utilisation of 80%

·        However, when the platform structure slips into the water the Lower, underwater Masaranduba beams become significantly lighter. This means the structure is 45.5 tons lighter (See below) and so lift utilisation is actually better at 66.7%

Lower Platform

Tons when Overwater

Tons when Underwater

Tons Lost

Pentagram Beams

5.1

0.9

4.2

Square Base Beams

7.7

1.4

6.3

Spoke Beams

5.6

1.0

4.6

Spider Beams

13.5

2.4

11.1

6”x6” Uprights

4.6

0.8

3.8

4”x4” Triangle Uprights

18.9

3.4

15.5

Total

55.4

9.9

45.5

·        The Phase Summary in the introduction includes the “Lift Utilisation” at the end of each phase.  This tells us how much of the lift capacity we are using. (If it was greater than 100% the pyramid would sink!). Note that the Lift Utilisation reaches its maximum of 83% at the end of the project. If the 148 tons of lift locked into the Topa Safety Buffer is included, the real Lift Utilisation is nearer 72% which is very safe.

 

"Phase 4 Task Summary"
(Excluding Costs) 

  Task KGs
     
1 Bottle Collection (Ring 1 & 5) 11,680
2 Spider Beams 41,646
3 Platform Structure 29,046
4 Floating 64,212
     
 

Totals:

146,584

 

 

"Phase 4 Task Overview"

·        In phases 1.3, 1.6 and 1.8 we saw how the basic platform structure had been started. (1.8 provides a good introduction)

·        The lift of 976 tons is provided evenly across the platform base of (38.39m)²

·        The weight distribution has been achieved with a spider-web design. The edges, centre and the Spoke Beams are all reinforced with 5/16th inch iron angle

 

·        Each ring numbered above has a different area and lift capacity:

Ring

Area (M²)

Volume (M³)

Lift (Tons)

Topa Volume (M³)

Topa Lift (Tons)

Raft Lift (Tons)

(x22/20)

1

157

197

113

24.6

17.2

18.9

2

232

292

168

36.5

25.4

29.9

3

307

386

222

48.3

33.6

37.0

4

383

481

277

60.2

41.9

46.1

5

270

340

196

42.5

29.6

32.5

Topa+

+250

-

-

39.2

-

30.3

Total

1350=1600

1695

976

251

148

193

 

·        Note: The “Topa+” accounts for the area that is not available to the bottles to lift the pyramid but that is nevertheless used by the temporary Raft base. (i.e. The pool, the cannel, outside edges, - it’s about 16 rafts worth).

·        Note: The volume is calculated by multiplying by the depth of 1.3m but then subtracting the volume lost to underwater beams

·        The weight of the pyramid mostly bears down on the edges and in a central 5 sided pyramid of approximately 12m diameter. Calculations suggest that about the same weight is bearing down on the centre as around the edges.

·        So, the architectural challenge has been to create a strong platform that absorbs the lift of the mid-area (between centre and edges) and distributes this lift to the sides and centre evenly, where it can absorb the pyramid’s weight. If the pyramid did not have this central structure then the job of distributing the lift to the edges would have been much more difficult. (The central pyramid area would want to explode upwards under the force of the bottles!)

 

The Distribution of Weight

·        Note that the spider web pattern of beams is repeated once above the water line in 8”x6” Masaranduba and again 1.5m below, underwater, in 7”x6” Masaranduba. The Upper Web distributes the lift of the bottles and absorbs the weight from above, it is very strong and reinforced with iron. All the joints are directed to respect the fact that the bottles push on the Topa, the Topa pushes on the Spider Beams, Spider Beams push on the Spoke Beams and finally the Spoke Beams push onto the Pentagram and Square Base

·        The Upper Spider Beams are joined to the Spoke beams as shown below and the Spoke Beams are joined to the edges and pentagram. The “Dovetailed Lap” joint is used with the height of the dove side being 4”. Joints on the square base will use the “#24: Mortised Rabbeted Oblique Scarf “ joint. Re. The “Art of Japanese Joinery” by Kiyosi Seike.

 

Dovetailed Lap Joinery

 

Paper drawing of Platform

·        The Lower Web can be considered to be hanging off the upper web and is not as strong. It’s primary function is to keep the bottles from shooting out the sides. There are 6”x6”x1.5m Masaranduba Uprights in between the two webs. These have dowel pins that are designed to take vertical load should the pyramid ever land due to drought. The diagonal uprights strengthen the sides and these are dove-tailed so that the Lower Web can hang off of the Upper Web. You can just see these in the photo of a drawing above

·        The Lower web is dove-tailed in the opposite direction so that the two webs are locked together and the inner beams are sandwiched inside. The pyramid is designed to land in flat soft clay

·        Experimentation of bottles in water under pressure will have been conducted. It will be known for example how many bottles fail and if using silicon inside the screw-top helps. Another experiment will be to find a liquid that can be dropped into the bottles before the cap is tightened. The liquid will then turn to gas and pressurise the bottle so that it can counter the pressure underwater and not get crushed

·        It will also be known the best way to package the bottles to maximise buoyancy. (The experiments below were with a random assortment in a random array). It is probable that the bottles will be placed evenly into big bags before being submerged. This is to make them more manageable and to keep mud from getting between the bottles should the pyramid have to land or get very low 

·        Fishing net is also utilised to keep bottles from escaping out the sides

 

Experiments with bottles

 

·        Experimentation to date has shown (altho outside of water) that a given volume filled with random plastic bottles will trap 57.53% of this volume inside the bottles. The experiment also yielded that 1m³ of bottles weighs 21.75kg and contains 493 random bottles. (The volume in the photo above was very carefully calculated excluding the inner timbers of the table for example)

·        This suggests that of the 1695m³ volume the platform provides, around 975m³ of water is displaced. This translates to 975 tons of lift

 

"Phase 4 Task Details"

 

4.1            Bottle Collection

·        Plastic bottles will fill the 1350m² area in ringed sections to a depth of 1.3m. Allowing some loss due to Masaranduba structure around 1695m³ of bottles will be used. (This is 36.9 tons of plastic bottles or around 836,000 random bottles). A random sample was taken at the collection depot in Iquitos and is typical with bottles ranging from the large 3.3 litre gaseous types down to the 0.5 litres.

·        All labels are to be removed, bottles rinsed twice, pressurised with a non toxic gas and the tops dipped in silicon before being screwed on tightly. The word “Love” or a heart shape will be written on the side of each bottle. (Re. Work of Japanese Dr Masaru Emoto)

·        By Phase 4, five months into the construction, it will be necessary to have collected 1/3rd of the bottles, that’s 12 tons. The Iquitos bottle recycling plant recycles 10 tons of bottles per month so the target of 2.4 tons/month is reasonable. This collection rate will continue until the end of the project; (2/3rds by November 2008, the rest by April 2009)

·        It is hoped that it is possible to get bottles donated for free over this longer period to avoid the high cost (S/. 1.20 per KG) and to improve quality

 

4.2          Spider Beams

·        In phases 1.3, 1.6 and 1.8 we saw how the basic platform structure had been started. The edges, central pentagram and Spoke Beams are in place. During this phase the rest of the work on the platform will be completed. Not all bottles will have been collected to gain maximum buoyancy but enough so that the repositioned Topa is out of the water

·        The Spider beams create 4 solid rings around the platform. The upper beams are 6” x 8” Masaranduba and the lower beams that are permanently in the water are 6” x 7” Masaranduba. The uprights are 6” x 6” and break the 12 spans greater than 9.6m

·        It is expected that adding the 64 Spider Beams and extra uprights will be a long job because much detailed carpentry of the joints is required

·        4”x4” diagonal uprights are added forming triangles between the upper and lower web of all the beams (Edges, Pentagram, Spoke beams and Spider beams). These are approximately 2m long making triangles, like mini-pyramids, every 2.65m approximately. These massively strengthen the structure in case of landing and ensure the lower web hangs off of the upper web. The joints are all dove-tailed and slide in from the side with the bottles pushing against them

·        There is currently no plan to reinforce the spider beams with either iron angular or high tension cable

 

4.3          Platform Structure

·        5” x 5” Anacaspi “Topa Support Beams” will be added as per the drawing. So too the 4” x 4” Anacaspi “Tabla Support Beams”

·        The nets will be added by weaving them between the 2 metre diagonal upright batons so distinct bottle areas are formed

·        The EN3 & ES3 section contains the band pit and so it is necessary to lower the Topa by 0.3m in this section. The Topa will also be skimmed by 2” to make way for tarred Masaranduba boarding. With no further boarding in the pit and with a one metre high stage the band will have 1.5m of height clearance. The lowered area sides are also boarded off with Masaranduba and tarred to prevent water penetration. Buoyancy lost to the Band Pit is only 3 tons and considered negligible in other calculations

 

4.4          Floating

·        Rings 1 & 5 will be filled first because these are closer to the edges where the pyramid weight is coming down from. The other 3 rings will be filled evenly as bottles arrive after Phase 4

·        The temporary Topa below will slowly be removed such that the pyramid sinks and depends on the bottles. As more Topa is available more sections will be prepared ready for bottles. By the end of the phase only 16 rafts will remain under the pyramid. Bottles can be added by swimming them underwater as they are collected

·        The 20cm cap of Topa holds the bottles down but it also provides an emergency extra buffer of 145 tons of buoyancy

·        When the rings are full and flat bottomed, plastic may be used to stop mud from entering from below (this is a contingency against the pyramid getting too low in the water or even landing). This is in conjunction with the fact the bottles are already in big bags that also combat mud. The danger is that mud gets between the bottles gluing the structure to the riverbed as the mud dries and adding unwanted weight to the pyramid. It is also a way of preventing fish from getting trapped between the bottles. Generally, it is preferable that water tends to get into the platform from higher up where mud is less likely to occur

·        In order to allow the river to flow through the pyramid platform and keep the swimming pool from stagnating, two underwater 14 metre pipes will connect the pool to the East side. This is in generally in the direction of river flow and will be complemented on the West side by the canal. The 2 pipes of 1/2m diameter will only displace 5.5m³ of bottles and so this is considered negligible to other calculations

·        Note that the final skin of floor boards over the Topa is not added in this phase

 

free page hit counter