Phase 9

 

Phase 9 Objective: “King’s Level Complete – (11 Hotel Rooms)”
By March 2009 (1 Month)

 

Phase 9 Objectives Discussed"

·        Kings adds 10 standard hotel rooms, a large dormitory, the marital suite, a library and a furniture store room. The number of guests can now double to 30-40 tourists

·        By now Casa de Julio is no longer a hotel. The Southern room is made into a workshop. The South-West toilet is taken into the adjacent room creating an ensuit bathroom

·        Massage, acupuncture, reflexology, tarot… etc. will now have the chance to begin because the room will be there. Whilst the pyramid is still lacking the platform facilities, these facilities will add value for guests

·        By now the pyramid will be employing 20 people but with the last 5 or so employees being specialised in the New Age arts. These people will probably be contractors rather than full time employees

·        The presentations should be becoming more practised and honed now

·        Altho a high tech hotel solution is still missing, the procedure for booking rooms and controlling keys etc should be well rehearsed by now

 

"Phase 9 Task Summary"
(Excluding Costs) 

  Task KGs
     
1 Kings Leaves 2,904
2 Kings Floor 23,511
3 Kings External Walls & Doors 13,792
4 Kings Internal Walls & Doors 18,676
5 Kings External Benches, Flora & Water 16,900
6 Kings Completed (Bathrooms, Ceilings, Balcon) 8,483
7 Kings Furniture & Décor 4,816
8 Bottle Collection By March 2009 12,604
     
  Totals: 101,685

 

 

 

 