The Pyramid Project |
|
Phase 12
Phase
12 Objective:
“Construction
Completion"
“Phase 12 Objectives Discussed" ·
July
2009 is ready for the tourist peak month. The pyramid may host the 2009 Shamen
Conference ·
In
the final 2 weeks all outstanding construction tasks must be completed or handed
over to the maintenance man. The full-time maintenance man will be taken from
the construction crew and added as a permanent employee of the pyramid ·
Get
all art finished and move out of construction mentality, focus now more on the
quality of service and on the bigger causes the pyramid must support ·
By
9th September 2009 all profit must now be diverted at the project
causes and not on more construction. Construction must end! ·
It
is hoped that between July and September 2009 Healthy Holidays will generate
enough capital so that the project can have a land based office in Iquitos ·
The
official opening, press date, for the pyramid will be 9th September
2009
"Phase 12 Additional Weight" ·
The
maximum capacity of the audience is 400. A weight of 80kg is allowed per person,
this is a safe, over estimation of the average person ·
When
the 44 employees, 90 tourists and tourist baggage is added on the total
additional weight is 50 tons ·
Note
that rain water capture was already added on in the weight of the water tanks |
|
|